Detailed Step by Step Guide in Setting Up NetSuite Supply Planning WorkBench

One of the Consultants, Rizwan at #Teampaapri wrote an article on the new Supply Planning Feature used in NetSuite. He went through step by step starting from setting up the supply planning engine to creating purchase order, sales order and Work Orders. I thought it would be a great article to share with Paapri followers as we do NetSuite ERP implementation and maintenance:

Supply Planning

All the steps are done via Administrator role.

What is Supply Planning?

NetSuite Supply Planning helps supply planners determine how to best establish criteria to fulfill demand plan requirements. Supply planning uses sales order details to generate dependent demand for work order components. The objective is to balance supply and demand to achieve your organization’s financial and service objectives.

fSupply plans generate a recommended schedule for purchasing or manufacturing items for supply. A supply plan lists the recommended purchase orders and work orders that can increase item supply based on lead times and expected demand. Planners can create multiple supply plans which can vary depending on the planner’s criteria, such as planning horizon, planning scope, and planning rules.

Supply Planning includes processes and steps that enable supply planners to balance supply and demand to achieve an organization’s financial and service objectives. The following diagram represents the NetSuite Supply Planning process:

file-1428412

Prerequisites for Supply Planning

Navigate to Setup -> Company -> Setup Tasks -> Enable Features.

1. Under the Items and Inventory subtab, the following features must be activated.

· Multi-Location Inventory – for the assembly item stock levels needed for the supply plan

· Assembly Items – to enable planning for manufactured items.

· Advanced Bills of Materials – where component assembly items are stored to ensure that the assembly components are available.

· Work Orders – the order that builds the assembly item must be included in the supply plan.

· Advanced Inventory Management – to include reorder point and safety stock levels in the supply planning run.

· Material Requirements Planning – to activate the supply planning feature.

· Demand Planning – to are use demand plans (forecasts) with supply planning.

· Advanced Item Location Configuration – This feature has not been mentioned in the SuiteAnswers. This has to be activated too.

file-7088014
file-3602006

Navigate to Setup -> Accounting -> Preferences -> Accounting Preferences.

Under the Order Management subtab, check the Allow Purchase of Assembly Items box.

file-4931903

Under the Approval Routing subtab, check the Purchase Orders box.

file-4880093

Navigate to Setup -> Accounting -> Preferences -> Inventory Management Preferences.

Check the Use lead Time and Safety Stock per Location box.

file-5861234

Setting Up an Item for Supply Plan

While setting up the item, under the Purchasing/Inventory subtab, select the Replenishment Method as Material Requirements Planning (MRP).

file-1799952

Under the Purchasing/Inventory (subtab) -> Location (sublist), edit the location for which you want to configure Planning details.

file-3144077

Under the Planning subtab, enter the Safety Stock Level, Purchase Lead Time. etc.

file-8555251

Inputs to the MRP

There are two inputs the MRP:

1. Supply Plan Definition – Supply Plan Definition enables planners to establish the criteria to be used for supply planning. The plan definition provides the information that drives the supply planning process, such as planning horizon and planning scope. For example: you can run supply planning at multiple facilities at one time. A supply plan definition provides a permanent holding place for your planning criteria and planning results.

2. Planning Repository – The Planning Repository stores related planning information that enables you to control how often NetSuite updates planning inputs. The repository refresh process accumulates the most up-to-date data from NetSuite to use for supply planning. The planning process calculates projected available quantity, generates supply orders, and action and exception messages.

file-5363867

Creating Planning Item Category

Navigate to Lists -> Supply Planning -> Planning Item Category -> New.

file-1757645

Give a name to Planning Item Category. User can also give a Description for the planning item category.

file-8367327

1. Save the record.

Open the Item Record, under Purchasing/Inventory subtab, for Planning Item Category, select the Item Category created in the above step from the dropdown list.

file-6917061

Note: For selecting a Planning Item Category the Replenishment Method has to be Material Requirements Planning or Master Production Scheduling.

Creating Planning Item Group

Navigate to Lists -> Supply Planning -> Planning Item Groups -> New.

file-2438400

Give a name to Planning Item Category. User can also give a Description for the planning item category.

file-1195464

Under the Planning Items subtab, for item type either select Planning Item Category or Item.

file-9384398

Select the Item Category created before.

file-5812453

Save the record.

Creating Planning Item Rule

Navigate to Lists -> Supply Planning -> Planning Item Groups -> New.

file-7566346

Give a name to Planning Item Category. User can also give a Description for the planning item category.

file-7335554

Under the Planning Items subtab, for item type either select Planning Item Category or Item.

file-4807418

Select an Item Category.

file-9379722

Select the Location for which you want Supply Planning.

file-1133328

Select a Source Location.

file-4115332

Enter the Lead Time in days.

file-4406287

Save the record.

Creating Supply Plan Definition

Navigate to Transactions -> Supply Planning -> Supply Plan Definitions -> New.

file-7897851

Enter a name for the Supply Plan Definition. Select the Planning Rule Group and Planning Item Group.

file-1926414

Select the location for which you want to create the supply plan definition.

file-6237369

Select their demand source type as either Sales Order or Demand Plans or Sales Order and Demand Plans.

file-4877558

Check the Consume Forecast checkbox. Save the record

file-1903421

Refreshing Planning Repository

Navigate to Transactions -> Supply Planning -> Refresh Planning Repository.

file-7494566

Select Complete Refresh to purge data from the repository and reload all item setup data and transactions for the supply plan. Select Net Change to reload data that has changed since the last repository refresh to present the latest supply planning data. Select a Refresh Option: Item Setup or Item Setup and Transactions.

file-3844235

If the user selects Net Change Refresh, the Refresh Options get enabled.

file-6459946

Select Item Setup or Item Setup and Transactions and select the Date Range.

file-7715184

Click on Refresh Data button.

file-3405772

The user can optionally select a Supply Plan Definition to launch it directly after the Repository has been successfully refreshed.

file-7608609

The Planning Repository Event Log page opens up. Here the user can see the status of the refresh and if there were any errors or not.

file-7651306

Launching Supply Planning Workbench from Supply Plan Definition

Navigate to Transactions -> Supply Planning -> Supply Plan Definitions

file-9445250

Click on the Launch button.

file-4596320

After this submission status becomes Complete for the process type Material Requirements Planning, click on View Results under Planning Workbench column.

file-7520849

Supply Planning Workbench

After clicking on the View Results hyperlink, the Supply Planning Workbench opens up.

file-8352309

The name of the Supply Plan Definition and other details is displayed on the top section.

file-8522067

Item Filters on the left section.

file-2883393

1. There are four different types of messages/outputs of the Supply Planning Workbench.

o Action – System’s recommendation for the supply plan.

o Exception – Challenges on the supply plan. Reasons behind the Late Demand quantity.

o Supply – Information regarding the Supply Orders included in the Supply Plan.

Demand – List of Demand Orders and Sources that needed to be fulfilled by the Supply Orders on the Supply Plan.

file-7960570

Below the Top section there are filters available to filter the messages.

file-4184545

User needs to perform the Actions for all items. Click on the number just below the Action column head. It is the summation of all the actions for all items.

file-3924470

User can also open the actions for individual items.

file-4117162

User can perform all the Actions one by one or all at once by checking the checkbox at the column head and clicking on Perform Selected Actions button.

file-4125507

After clicking on the Perform Selected Actions button, user will get a prompt from NetSuite. User needs to click on OK.

file-2547573

Click on the Refresh Data icon.

file-5803756

User can see the exceptions under the Exceptions subtab.

file-1754274

User can see the Supply Orders under the Supply subtab. Complete them if required by checking the checkboxes and clicking on the Release Selected Order or Create Planned Orders accordingly.

file-1925655

User can view the Demand Orders under the Demand subtab.

file-6688156

Converting Planned Purchase Orders to Purchase Orders

Navigate to Transactions->Supply Planning->Order Items.

file-5539392

Under the Planned Orders subtab, the Released Planned Purchase Order will be listed. Select the ones to be converted to Purchase Orders.

file-6925380

Scroll to the right and review other details. Submit the record.

file-6028367

A PO gets created.

file-9111056

After receiving this PO, user needs to convert the Planned Transfer Order into Transfer Order.

Converting Planned Transfer Order to Transfer Order

Navigate to Transactions->Supply Planning->Replenish Location By Transfer Order.

file-5486344

Under Planning subtab, select the Planned Transfer Orders to be converted.

file-6409143

Review other details and submit the record.

file-6982632

A Transfer Order gets created.

file-1621894

Converting Planned Work Orders to Work Orders

Navigate to Transactions->Supply Planning->Mass Create Work Orders.

file-9156170

Under Planned Orders subtab, select the Planned Work Orders to be converted.

file-5781067

Review other details and Submit.

file-9368075

On the Process Status page, click on the Submission Status hyperlink to view the created work orders.

file-3246353

The details of the Work Orders gets listed.

file-7398276
file-7360825

Hope this helps. I also added a NetSuite Demonstration on Supply Planning WorkBench